1. A mid-size desert array
At 91 MW the plant still faces full desert conditions: high ambient temperature, dust and strong irradiation. The protection design concentrates on a clean, serviceable combiner layer rather than extreme scale.
2. Combiner and DC protection
- PV combiner boxes rated to 1500 V DC collecting strings with individual gPV fuse protection.
- DC disconnect switches for safe isolation.
- Type 2 DC SPDs staged to the 1500 V envelope.
- DC MCBs for auxiliary circuits.

3. Selective coordination
The gPV fuse and downstream protection were coordinated so a single string fault clears locally without dropping a feeder. This keeps the plant availability high with a small maintenance team.

4. Desert derating
- Current parts derated for sustained heat and solar gain.
- Enclosure to IP65 with a corrosion class for inland dust.
- SPD staging reviewed for local lightning density.
5. Outcome
The protection scope gave the plant a reliable, easy-to-maintain foundation. The lesson for mid-size desert plants is that disciplined combiner and SPD design matters as much as at gigawatt scale.
Final ratings, coordination, installation and applicable local requirements must be verified against current standards, manufacturer documentation and the approved project design.
Frequently asked questions
What protects a 91 MW desert array?
A layered chain: gPV fuses at each string, DC disconnect and DC SPD in every combiner, DC MCBs for auxiliaries, and coordinated low-voltage switchgear.
Does plant size change the protection?
The devices are the same; the difference is scale of coordination. A mid-size plant still needs full desert derating and selective fault clearing.
Which standards apply?
IEC 62916, IEC 60269-6, IEC 60947-2, IEC 61643-31 and IEC 61439.
Why derate for desert heat?
Ratings applied against the site ambient keep protection devices within their temperature bands under peak load.
Bring the array and environment inputs to review.
Share the string, site and collection requirements for a serviceable protection scope.
Discuss a projectContinue learning
Explore related technical guidance in Solar PV.
Published from the approved Period 12 source package; project, technical and standards statements are retained from the supplied publication content.